Ivanhoe Electric is planning to use a remanufactured 9.3m-diameter Robbins Crossover XRE TBM to excavate a 4km-long mine access decline at its Santa Cruz Copper Project in Arizona, where the company has now secured an indication of up to US$1.1bn in potential debt financing.
A portion of the machine components have been used previously for the excavation of two declines at Anglo American’s Grosvenor coal mine in Queensland, Australia, These components along with newly manufactured components are expected to arrive for assembly in Arizona in the first quarter of 2027. Tunnelling is scheduled to start in the third quarter of that year, with the 4km drive targeted for completion in approximately 12 months.
The US Export-Import Bank (US EXIM) has issued Ivanhoe Electric with a Preliminary Project Letter (PPL) for potential financing of US$1.1bn for Santa Cruz, up from the US$825M indicated in an April 2025 Letter of Interest.
The financing remains subject to further review and approval, with final US EXIM board consideration anticipated in spring 2027.
Ivanhoe Electric identified the availability of the Robbins TBM in late 2025 and secured a binding option to acquire it from Robbins in March this year. Robbins, in turn, agreed to reacquire the machine from Anglo American.
The Robbins Crossover XRE is designed for variable ground, the machine can operate through hard rock, in pressurized or EPB mode for wet and running ground and mixed-face conditions during a single drive. Ivanhoe Electric said investigations at Santa Cruz indicate that these conditions will be encountered during decline construction.
The machine combines EPB capability with a bi-directional cutterhead and high-torque cutterhead drive. Its EPB mode allows the cutterhead chamber to be pressurised against groundwater to maintain face stability and control inflows when crossing water-bearing zones and aquifers.
During excavation, the TBM will erect a continuous sealed lining of steel-reinforced precast concrete segments, creating a permanent flat-bottomed decline. The system will also incorporate a permanent conveyor which has also been designed and supplied by Robbins which will initially remove excavated material during the TBM boring operations before being retained for ore handling during mine production.
Robbins will carry out a substantial overhaul and remanufacturing of the TBM before delivery to Arizona, including complete refurbishment of the 9.3m-diameter cutterhead at its facilities in Ohio. The TBM will also receive updated technology and modifications tailored to the anticipated Santa Cruz geology.
Ivanhoe Electric puts the acquisition cost of the TBM and material handling system, including refurbishment, at approximately US$64.7M.
The mechanised tunnelling solution replaces the roadheader excavation, silica gel grouting and Railveyor material handling system proposed in the project’s 2025 Preliminary Feasibility Study (PFS). Ivanhoe Electric estimates the resulting net increase in initial project capital at less than US$20M.
The change also removes the requirement for a Class V Underground Injection Control permit associated with the proposed silica gel grouting.
Box-cut excavation for the decline is scheduled to begin in the third quarter of 2026. Following TBM excavation from Q3 2027, underground mine development is scheduled to begin in Q3 2028, with first copper cathode production targeted for Q2 2029.
The TBM could have a role beyond the initial Santa Cruz development. Ivanhoe Electric said ownership of the machine would give it the capability to pursue future expansion, including development towards the Texaco copper deposit approximately 2km northeast of Santa Cruz.
An updated PFS, expected in September, will incorporate the TBM decline, material handling system and engineering work undertaken since the 2025 study.
US EXIM’s PPL follows preliminary due diligence on Santa Cruz and represents a step towards a potential financing agreement rather than a firm funding commitment. The application is being considered under the bank’s Make More in America Initiative, which supports US projects intended to increase domestic production and strengthen critical supply chains.
Santa Cruz is planned as an underground operation producing 99.99% pure copper cathode onsite without conventional smelting.
Comments:
Facts Only
* Ivanhoe Electric plans to use a remanufactured 9.3m-diameter Robbins Crossover XRE TBM for a 4km mine access decline at the Santa Cruz Copper Project in Arizona.
* The company has secured an indication of up to US$1.1bn in potential debt financing.
* Machine components were previously used for two declines at Anglo American’s Grosvenor coal mine in Queensland, Australia.
* Components and new parts are expected for assembly in Arizona in Q1 2027.
* Tunnelling is scheduled to start in Q3 2027, with the 4km drive targeted for completion in approximately 12 months.
* The US Export-Import Bank (US EXIM) issued a Preliminary Project Letter (PPL) for potential financing of US$1.1bn.
* Ivanhoe Electric secured a binding option to acquire the Robbins TBM from Robbins in March 2025, which agreed to reacquire the machine from Anglo American.
* The Robbins Crossover XRE is designed for variable ground conditions, operating in EPB mode for wet or running ground.
* Excavation will involve erecting continuous sealed lining of steel-reinforced precast concrete segments.
* A permanent conveyor system will be incorporated into the TBM design for material removal and ore handling.
* The acquisition cost for the TBM and material handling system, including refurbishment, is estimated at approximately US$64.7M.
* Box-cut excavation is scheduled to begin in Q3 2026.
* Underground mine development is scheduled to begin in Q3 2028, with first copper cathode production targeted for Q2 2029.
Executive Summary
Ivanhoe Electric is planning to excavate a 4km mine access decline at the Santa Cruz Copper Project in Arizona using a remanufactured 9.3m-diameter Robbins Crossover XRE TBM. This project is supported by an indication of up to US$1.1 billion in potential debt financing from the US Export-Import Bank (US EXIM), following a Preliminary Project Letter (PPL). Machine components are being sourced, with some parts from previous use at Anglo American's Grosvenor coal mine in Queensland, Australia. The machine and newly manufactured components are expected to arrive for assembly in Arizona in Q1 2027, with tunnelling scheduled to commence in Q3 2027 and completion targeted within approximately 12 months.
The Robbins Crossover XRE TBM is designed for variable ground conditions, including hard rock and pressurized/EPB modes suitable for wet or running ground, utilizing a bi-directional cutterhead and high-torque drive. The tunneling method involves erecting a continuous sealed lining of steel-reinforced precast concrete segments and incorporating a permanent conveyor system provided by Robbins. The acquisition cost for the TBM and material handling system, including refurbishment, is estimated at approximately US$64.7 million.
The proposed mechanised tunnelling solution replaces previous methods like roadheader excavation and silica gel grouting, estimating a net increase in initial project capital of less than US$20 million and eliminating the need for a Class V Underground Injection Control permit. The TBM ownership is intended to allow for future expansion into nearby deposits, such as the Texaco copper deposit.
Full Take
The narrative frames a high-capital infrastructure project leveraging specialized, re-engineered technology to achieve resource extraction, positioning the TBM not merely as equipment but as an integrated solution that bypasses conventional, permitting-heavy methods like grouting and roadheader excavation. The pattern observed is the strategic juxtaposition of historical component use (Anglo American) with future financing mechanisms (US EXIM PPL), suggesting a reliance on established industrial supply chains to mitigate novel execution risk. This structure suggests an attempt to establish legitimacy through established precedent while chasing ambitious technological integration.
The shift from specifying material handling and grouting systems (which required specific permits) to adopting the TBM system that eliminates those requirements speaks to a pattern of minimizing regulatory friction by embedding necessary functions within the machine itself. The implication is that technological advancement can be used as an instrument for risk reduction, shifting financial focus from environmental/regulatory compliance costs to upfront capital expenditure. This invites inquiry into whether this method truly represents innovation or simply a repackaging of known industrial execution strategies under a new technological veneer.
The long-term potential noted—the ability to pursue expansion toward adjacent deposits—suggests the TBM’s value extends beyond the immediate mine site, creating an asset with embedded strategic mobility. The question remains: if the technology is successfully deployed, does this pattern establish a precedent where specialized capital expenditure on complex machinery becomes the default path for high-grade resource access, potentially overriding broader considerations of environmental or social impact that are typically addressed in feasibility studies? What are the unseen costs associated with relying on remanufacturing and contingent financing timelines to drive forward such large-scale, long-term ventures?
