TBM prepares to bore München’s second cross-city S-Bahn tunnel
GERMANY: The first tunnel boring machine for the construction of München’s second S-Bahn crossing has been presented by manufacturer Herrenknecht.
Named ‘Donna Maria’ in a vote by local residents, the TBM is scheduled to start boring an initial 3 km section of emergency access tunnel on September 17. This will be followed by the 7 km main drive, for which work is expected to begin in 2028.
Comprising two single bores of 6.4 km, and a total of 600 m cut-and-cover sections at the two portals, the second S-Bahn line will largely run parallel to the existing east-west tunnel between Laim in the west and Leuchtenbergring in the east. It will be accompanied by the emergency tunnel, meaning three bores will be needed along the alignment overall.
The cross-city tunnel will form the principal element of the second München S-Bahn programme, on which works began in April 2017. In total, 11 km of new alignment will be required.
Tunnelling will be undertaken by the ARGE Tunnel Hauptbahnhof consortium, comprising Wayss & Freytag Ingenieurbau, the Max Bögl Group, Ed Züblin, and Bauer Spezialtiefbau.
The Herrenknecht TBM is 178 m long, weighs 700 tonnes, and has a diameter of 5 m. The tunnels for the second S-Bahn crossing will be located at a depth of around 40 m.
The launch of work at Ostbahnhof station in October 2025 means that construction is now in hand on all the sections of the corridor. Laim and Ostbahnhof stations are being rebuilt, and new underground platforms will be added at Hauptbahnhof and Ostbahnhof, as well as an intermediate station at Marienhof.
The original S-Bahn tunnel in München opened in 1972 ahead of the city hosting the Olympic Games, but it is now reaching the limit of available capacity.
See also
Subscribe to gain access to all news
Already have a subscription? Log in.
Choose your subscription
Considering a corporate subscription? Contact us to find out more.
Facts Only
* Manufacturer Herrenknecht presented the TBM 'Donna Maria'.
* The TBM is 178 m long, 700 tonnes, and 5 m in diameter.
* Boring of a 3 km emergency access tunnel starts September 17.
* A 7 km main drive is scheduled to begin in 2028.
* The project includes two 6.4 km single bores and 600 m of cut-and-cover sections.
* The alignment runs between Laim in the west and Leuchtenbergring in the east.
* Total new alignment required is 11 km.
* Tunnels will be located at a depth of approximately 40 m.
* The ARGE Tunnel Hauptbahnhof consortium (Wayss & Freytag Ingenieurbau, Max Bögl Group, Ed Züblin, Bauer Spezialtiefbau) is performing the tunnelling.
* Work at Ostbahnhof station begins October 2025.
* Reconstruction includes Laim and Ostbahnhof stations, plus new platforms at Hauptbahnhof and Ostbahnhof and a new station at Marienhof.
* The existing S-Bahn tunnel opened in 1972.
Executive Summary
München is expanding its S-Bahn capacity through the construction of a second cross-city tunnel, a primary component of the second S-Bahn programme initiated in 2017. The project aims to alleviate congestion in the original 1972 tunnel system, which has reached its operational limit. The expansion involves 11 km of new alignment, consisting of two main bores and an accompanying emergency access tunnel, running largely parallel to the existing east-west route between Laim and Leuchtenbergring.
Construction is now active across all corridor sections. The immediate phase begins with the 'Donna Maria' TBM boring a 3 km emergency section on September 17, followed by the main drive in 2028. Infrastructure upgrades include the rebuilding of Laim and Ostbahnhof stations, the addition of underground platforms at Hauptbahnhof and Ostbahnhof, and the creation of a new intermediate station at Marienhof. The project is being executed by the ARGE Tunnel Hauptbahnhof consortium using specialized equipment from Herrenknecht.
Full Take
The narrative presents a straightforward engineering milestone: the deployment of a TBM to solve a capacity crisis in urban transit. The strongest version of this story is one of necessary civic evolution—updating 50-year-old infrastructure to meet the demands of a growing modern metropolis.
This reporting is purely descriptive and avoids persuasive framing; it functions as a technical announcement rather than an argument. It provides specific metrics (depth, weight, length) to establish transparency and scale without employing emotive language to manufacture urgency.
Patterns detected: none
The underlying paradigm is one of "technological solutionism"—the assumption that the primary answer to urban congestion is the expansion of physical throughput via massive engineering projects. While these projects provide tangible utility, the unstated assumption is that demand for this specific transit corridor will continue to scale linearly or exponentially, justifying the immense capital expenditure and decades-long timeline. The primary beneficiaries are the state's transit authority and the industrial consortiums involved, while the costs are borne by the public treasury and those living above the 40-meter depth line.
If this were part of an influence campaign, a bad actor would emphasize the "inevitable collapse" of the current system to stifle debate over alternative transit models or cost overruns. The current content does not match this pattern; it remains a neutral report of scheduled works.
Bridge Questions:
1. How does the projected capacity increase compare to the actual growth in ridership forecasts for 2028 and beyond?
2. What alternative transit strategies were considered before committing to a second deep-bore tunnel?
3. What are the projected environmental and surface-level disruptions during the seven-year gap between the emergency tunnel and the main drive?